Management of the Metal Removal Fluid Environment

Flume Design


Back Home Up Next

Table of Contents
Getting Started
Glossary
Search
Information&Links
On this page:
types of flume systems
flume requirements for different metals
high-vol./low pressure flushing

How are flumes designed?

To return spent metal removal fluid and chips generated by the machining operations, central systems utilize trenches (flumes) in the plant floor. For better MRF and chip flow, the trenches are sloped down to the filter tank. Flush nozzles piped from the MRF system pumps are used to assist in carrying the chips through the flumes. Flumes are installed so the top surface of the liners and the cover plate are flush with the surrounding floor or deck.

Flumes should be located immediately below the machine discharge chute and should be wide enough to contain the chip and MRF discharge. Flumes are usually supplied in standard widths of 9", 12", 15", 18", 24" and 36". Flume width should also be based on the quantity of MRF flowing through the flumes. Flumes should be sized and pitched to maintain an MRF velocity of 6-10 ft./sec., depending on the material being machined.
Most flume systems are installed with a 1/8" per foot slope to the filter tank. Flush nozzles are installed at intervals (usually every 20-32 feet, depending on the application) throughout the flume system to move chips and maintain MRF velocity. The flume sections at these nozzles are built so the flow from the nozzle is discharged below the MRF flowing through the flume. Each of these step-flush boxes results in a 2" to 2-1/2" drop in trench elevation.
The pitch of the flumes, number of step-flush nozzles, and length of the trench runs will determine the depth of the metal removal fluid pit. The pit construction cost increases significantly with increased depth. Deep pits usually require sheet piling and de-watering. Pit depth can be minimized if the pit can be located in the center of long trench runs rather than at the end.
Flumes are constructed in approximately 20-foot sections of a 10-gauge steel liner formed into a "U" shape. The "U" type construction should transition from a round cross-section, to a half-round, to a rectangular cross-section at all changes in direction. Changes in direction should be accomplished with 3-foot (inside) radius turns. Flume sections should be welded watertight (no stitch welding), including curb angles. Section joints should be ground to provide smooth MRF flow.
Flume cover plates are required in all areas not covered by machines. Covers should be made from 3/8", 1/2" or 5/8" thick non-slip ("Slip-Not," "E-Z Weld," etc.) safety plate capable of supporting 250 PSF. When crossing an aisle, the top of the trench should be recessed 8 inches and a 10-gauge cover welded to the liner. Reinforced concrete is then poured over the trench to complete the aisle.
The use of flume systems to move chips should be minimized. While flumes and other sources of aerosol generation should be covered, an enclosed flume spillway can cause the mechanically generated mist to be blown back at the machine operator. Venting the flume to the metal removal fluid reservoir, if it’s practical to do so, will reduce this problem.

 Are there different types of flume systems?

When engineering flumes for a central system, the primary consideration is the type of material being machined. Flume systems are usually classified as aluminum, cast iron, or steel. Each material has its own characteristics and related problems. There are different requirements and considerations. The following sections show typical requirements and considerations for each material.

Aluminum

Aluminum chips are light and, therefore, easier to transport through the flumes. While aluminum turning operations produce some long, stringy chips, they usually do not form large springy bundles.
Metal removal fluid velocity should be maintained at 6-8 ft./sec. Flush nozzles are usually spaced at 30-foot intervals, with a trench slope of 1/16" to 1/8"/ft. MRF required for trench flush is approximately 1-1/2 to 2 GPM/ft. of trench.

Cast Iron

Cast iron and nodular iron break up into small, heavy granular chips that move readily through the trench if MRF velocity is adequate.
MRF velocity should be maintained at approximately 10 ft./sec. MRF required for trench flush is approximately 2 to 2-1/2 GPM/ft. of trench. Normal spacing for flush nozzles is approximately 20 feet.

Steel

Steel chips can vary in size and shape, from very small granular pieces to long, stringy curls on turning operations. It is the long, stringy curls that intertwine and collect to form large bundles, which are very difficult to move through the trench. The problem with bundles usually starts with the machine not discharging the chips efficiently. Often, long, stringy chips are hung up in the machine discharge and are allowed to accumulate there from a number of parts before the operator manually clears the machine. The operator usually uses a stick or rake to push the accumulated bundle through the machine into the trench. When the bundle is forced through the machine discharge, it compresses until it enters the trench, where it springs back out. At that point, it may become lodged in the trench. The trench should be wide enough to accept the bundles as they spring back out after being compressed.
MRF velocity should be maintained at 10 ft./sec. through the trench. MRF flow required for trench flush is 2-1/2 to 5 GPM/ft. of trench, depending on the type of chips expected. Flush nozzles are usually spaced every 20 feet but should be located near operations where bundles are expected.

The table below summarizes the different requirements for the different metals.


Flume Requirements

 

MRF Velocity

MRF Flow

Nozzle Spacing

Other

Aluminum

6-8 ft./sec.

1-1/2 to 2 GPM/ft

30-foot intervals

trench slope of 1/16" to 1/8"/ft

Cast Iron

10 ft./sec.

2 to 2-1/2 GPM/ft

20 feet

 

Steel

10 ft./sec

2-1/2 to 5 GPM/ft

  place nozzles where
bundles expected

 

The above discussion centers on flume systems that use stepped flushes and flush nozzles. However, recently another kind has been used for aluminum machining and ferrous fine grinding operations: high-volume/low-pressure trench flushing.

What is high-volume/low-pressure trench flushing?

These systems have only high-volume MRF supply pipes at the shallow end of each trench run; there are no intermediate flush nozzles. The trench slope is varied from 0 to 3/8"/ft. throughout the system to maintain 6 ft./sec. MRF velocity. These systems have performed well to date.

There are some advantages to this type of flushing:

easier trench installation and fabrication
lower mist generation
lower piping costs because there are few flush drops
less expensive trench liners—no step flush boxes to fabricate
lower energy consumption
The only disadvantage is that if problems moving the chips are encountered at certain operations, there are no intermediate nozzles where flow can be increased.


back to top

 

 

orc_logo_dc1.gif (10085 bytes)Contact Chris Roman, orcstaff@orc-dc.com  
Copyright © 1999 Organization Resources Counselors
All rights reserved. 
Revised: January 10, 2000

Prepared by AWARE Services   wpe47.jpg (1343 bytes)